The VDA published the next version of the Information Security Assessment catalogue on 1 July 2026. If you have been searching for “ISA 7.0”, this is what you are looking for, but the name has changed. Version numbers are gone, replaced by a year-based scheme, and this release also begins an annual publication cycle rather than the multi-year gaps everyone had grown used to.
The date that matters commercially is straightforward, and it is more generous than most write-ups suggest. ISA 2027 is mandatory for every TISAX assessment ordered from 1 January 2027 onwards. The trigger is the order date, not the completion date.
That distinction is the whole story. If you order before 31 December 2026, the assessment runs on ISA 6.0.3, even if the audit itself happens well into 2027. During the previous transition, ENX confirmed that this extended to corrective action plan assessments, follow-ups and scope extensions as well. An assessment procedure opened in 2026 therefore stays on the old catalogue for its full lifecycle rather than just its first appointment.
So there is a real decision in front of anyone currently thinking about TISAX, and it is worth making deliberately rather than by drift.
First, the thing most people are actually worried about
If you hold a valid TISAX label, it stays valid until it expires. Labels run on a three-year cycle, and a new catalogue release does not shorten yours. You will meet ISA 2027, or by then possibly a later annual edition, at your next renewal on your existing schedule.
Nothing about 1 January 2027 requires you to do anything early. The question is only relevant if you are ordering a new assessment, whether that is a first label, an additional scope, or a renewal that happens to fall near the boundary.
What has actually changed
Less than the naming shake-up suggests, and more than a cosmetic update.
Information security keeps its 46 controls. The overall structure holds. What has tightened is the wording: requirements that previously sat at “should” have, in places, been promoted to “must”, and some requirements have moved between protection-need levels. If your ISMS was built to clear the minimum bar under ISA 6, those promotions are precisely where new gaps will surface.
The supply chain gains real weight. Control 1.2.4, covering external IT service providers, moves out of Chapter 1 and into the supplier chapter as 6.1.3, which is a signal in itself. The obligation to assess and document how the ISA controls apply to each IT service provider carries over, but the catalogue now names the output a Supplier Statement of Applicability for the first time. Alongside it, 6.1.1 gets sharper: for high protection needs, supplier security evidence has to be documented and reviewed regularly, and whenever changes occur; for very high protection needs, the expectation moves to a third-party audit or an appropriate TISAX label held by the supplier.
That last point deserves a moment. If you sit at a very high protection need, you may find that satisfying the standard now depends on suppliers you do not control getting their own house in order. That is not a documentation task you can close out in a quarter, and ordering early only postpones it.
Prototype protection is rebuilt. The module drops from 22 controls to 20, and the structure changes materially: five sections collapse into two, covering organisational and physical security, with controls merged and outdated content removed. If prototype protection is in your scope, your evidence trail is currently organised against a structure that will no longer exist. Remapping is unavoidable.
Data protection is untouched, retaining its 12 controls.
The reference mappings are tidied up. References to the withdrawn ISO/IEC 27001:2013 are gone, and the mappings to ISA/IEC 62443 have been clarified, which matters if you are running TISAX alongside either standard or across shopfloor and OT environments.
Readability was a stated priority. The working group reviewed wording, translations, formatting and requirement structures to strip out long-standing ambiguities, and phrases that assessors and auditees had been interpreting differently now carry formal definitions. It is an unglamorous change, but it removes a category of argument you previously had to win on the day.
So should you order before December?
Because the trigger is the order date rather than the completion date, this is a cheaper decision than the deadline framing implies. You are not committing to being audit-ready in December. You are choosing which catalogue your assessment will be judged against.
Order under ISA 6.0.3 if you are already building against it. If your ISMS, evidence and internal audit were all designed around ISA 6, switching catalogues mid-preparation is rework you did not budget for and buys you nothing. Get the assessment procedure opened before the year turns and finish it at a sensible pace.
Order under ISA 6.0.3 if prototype protection is in scope and you are mid-programme. This is the strongest case of the three. The module has been rebuilt rather than adjusted, and remapping a live evidence trail against a structure that no longer exists is the single largest piece of avoidable work in this transition.
Go straight to ISA 2027 if you are starting from scratch. This is the case for deliberately not beating the deadline. If you have no ISMS yet, building one against a catalogue that has already been superseded means adapting twice within a three-year label cycle. Build once, against the version you will actually live with.
Two things are worth checking rather than assuming. Opening an assessment procedure is not a free option: your audit provider will have commercial terms, and there are limits on how long a procedure can remain open before it has to progress. Ask what those are for your provider rather than treating December as a cost-free placeholder. And if you sit at a very high protection need with thin supplier evidence, ordering early defers that problem by three years rather than solving it. You will meet the same suppliers again at renewal.
The blunt version: the catalogue you are assessed against matters far less than whether your management system actually works. Beating the deadline is worth doing when it saves you rework. It is not worth doing to avoid preparing properly.
If you’re deciding this quarter
Work out which side of the line you want to be on before the decision makes itself. That means checking whether prototype protection is in scope, establishing whether you are adapting an existing ISMS or building a new one, and—perhaps the one people skip—asking your audit provider both what their diary looks like and how long they will let a procedure stay open. Provider scheduling has always been the real constraint on TISAX timelines, and a cluster of organisations opening procedures before 31 December is unlikely to make that easier. The catalogue deadline is fixed. Assessor availability is not.
If you are going to meet ISA 2027 either way, the useful work is a gap review against the substantive changes: the “must” promotions in information security, the supplier chapter, and prototype protection where it applies. Organisations that look at those chapters early handle the transition as routine maintenance. Those that wait tend to treat it as a project.
We are currently supporting a global vehicle logistics operator through a Shared Group Assessment at Level 3, and our TISAX leads have held Certification Lead roles in-house rather than only advising from the outside. If you want an unsentimental view on whether to order before December or prepare properly for the new catalogue, that is a conversation worth having early rather than in November.
For more information, check out our TISAX Certification Support here.
*
Note on sources and timing: ISA 2027 was published by the VDA on 1 July 2026 and applies to assessments ordered from 1 January 2027, in line with the ENX Association’s announcement. Some of the accompanying process documentation for audit providers was still being finalised at the time of writing, so operational detail may be clarified further. We review this article following each annual catalogue release.